The Business Organization · 5 min read
Project Organization
Project Delivery Methods
Design-Bid-Build
Design-bid-build represents the traditional delivery method where owners engage design professionals to complete construction documents before soliciting contractor bids. The sequential process separates design and construction responsibilities. Owners contract separately with designers and contractors, maintaining direct relationships with each.
Contractors bid based on completed documents, theoretically enabling accurate pricing with minimal contingency. The low bid typically wins competitively bid projects. Disadvantages include extended schedules since construction cannot begin until design completion and adversarial relationships where contractors have incentive to maximize change orders.
Design-Build
Design-build consolidates design and construction responsibility under a single entity. Owners contract with design-build firms providing both services, creating single-point accountability. Design-build enables fast-track scheduling where construction begins before design completion. Early contractor involvement can improve constructability and reduce costs.
Design-build contractors assume greater risk since they commit to prices before completing design. Selection methods may emphasize qualifications and proposed approaches rather than low price alone. Design-build works well for projects with clear functional requirements but less well for projects requiring design excellence as primary objective.
Construction Management
Construction management at-risk positions the construction manager as an advisor during design who then assumes contractor responsibility during construction. The CM provides preconstruction services including estimating, scheduling, and constructability review. After establishing a guaranteed maximum price, the CM contracts directly with trade contractors and assumes responsibility for delivery within the GMP.
Construction management agency involves the CM serving as owner's advisor throughout the project without assuming contractor risk. The owner contracts directly with trade contractors while the CM coordinates activities. Agency CM works well for sophisticated owners wanting control over trade contractor selection.
Integrated Project Delivery
Integrated project delivery creates multiparty agreements among owners, designers, and contractors sharing risk and reward. IPD emphasizes collaboration, transparency, and collective project success over individual party interests. Contracts typically include shared contingencies and incentive pools distributing savings among participants. IPD requires high trust levels and works best with experienced teams committed to collaborative approaches.
Project Team Structure
Owner's Team
Owners assemble teams matching project complexity and internal capabilities. Owner's project managers coordinate internal stakeholders and manage external consultants and contractors. Large organizations may include separate representatives for operations, maintenance, finance, and legal functions. Owner's representatives may include specialized consultants for program management, commissioning, or technical oversight.
Design Team
Architects lead design teams for building projects, coordinating engineering consultants for structural, mechanical, electrical, and plumbing systems. Civil engineers lead site development and infrastructure projects. Interior designers, landscape architects, and specialty consultants address specific project requirements. Design teams develop construction documents defining project scope for contractor execution.
Contractor's Team
General contractors assemble teams scaled to project requirements. Project executives provide senior oversight for major projects. Project managers handle overall project delivery responsibility. Superintendents manage field operations and craft labor. Project engineers support technical functions including submittals, RFIs, and quality control. Administrative staff handle documentation, accounting, and clerical functions.
Subcontractors provide specialty trade services under contract with general contractors. Major trades include mechanical, electrical, plumbing, structural steel, concrete, roofing, and finishing trades. Subcontractor coordination represents a critical project management function.
Communication and Documentation
Communication Protocols
Effective project execution requires clear communication protocols establishing methods, frequencies, and responsibilities for project communications. Project directories identify team members with contact information and roles. Communication matrices specify who receives which types of information.
Regular meetings maintain coordination among project participants. Preconstruction meetings establish project procedures and relationships. Progress meetings track schedule and budget performance. Coordination meetings address technical interfaces among trades. Safety meetings reinforce safe work practices. Meeting minutes document discussions and action items.
Documentation Requirements
Construction projects generate extensive documentation requiring organized management. Contract documents define scope, terms, and conditions. Shop drawings detail fabrication requirements for contractor review and approval. Submittals include product data, samples, and certifications demonstrating specification compliance.
Requests for information seek clarification of design intent. Change orders modify contract scope, price, or time. Daily reports document work activities, weather, manpower, and significant events. Progress photographs record construction sequences. Correspondence files maintain written communications. Closeout documents include warranties, manuals, as-built drawings, and required certifications.
Document Control Systems
Document control systems ensure project participants access current information. Version control prevents work based on superseded documents. Transmittals track document distributions with receipt confirmation. Document logs track submittals, RFIs, and other items requiring response.
Modern projects employ web-based project management systems enabling real-time document sharing and collaboration. Systems track document status, manage workflows, and maintain audit trails. Mobile access allows field personnel to retrieve current documents and capture information on-site.
Scheduling and Coordination
Schedule Development
Project schedules establish timelines for construction activities. Work breakdown structures divide projects into manageable components. Activity sequencing identifies predecessor and successor relationships among tasks. Duration estimating determines time requirements for each activity.
Critical path method scheduling identifies the longest path through the project network determining minimum project duration. Activities on the critical path have zero float, meaning any delay extends project completion. Activities off the critical path have float allowing schedule flexibility without affecting completion.
Resource loading assigns labor, equipment, and materials to scheduled activities. Resource leveling adjusts schedules to avoid resource overallocation. Cost loading assigns budget values to activities enabling earned value tracking.
Schedule Management
Schedule management maintains alignment between planned and actual progress. Progress updates record actual start and finish dates plus completion percentages. Schedule analysis compares current status against baseline identifying variances.
Recovery schedules address delays through acceleration, resequencing, or scope adjustment. Schedule compression techniques include fast-tracking overlapping activities and crashing adding resources to critical activities. Time-cost tradeoff analysis evaluates acceleration costs against delay costs.
Coordination Requirements
Construction coordination aligns work among multiple contractors and trades. Trade coordination meetings review upcoming work sequences and identify conflicts. Coordination drawings overlay multiple trade systems identifying spatial conflicts before installation.
Building information modeling enables three-dimensional coordination detecting clashes among architectural, structural, and MEP systems. Clash detection identifies conflicts for resolution before field installation. Four-dimensional BIM adds schedule information enabling visualization of construction sequences.